Hagaajinta nidaamka

Shaqaalaha khadka ee bedelaya tiirka

PUD waxa ay macaamiisheenna ku haysay laydhka iyo korontadu in ka badan 70 sano. Kalsoonidu waa qiimaha asaasiga ah shaqada aan qabano maalin kasta waxay hubisaa inaan bixino awoodaas joogtada ah.

Dhowrka sano ee soo socda, PUD waxay fulin doontaa hagaajinta nidaamka korantada iyo mashaariicda dayactirka ka hortagga si ay u caawiso hubinta heerarka sare ee kalsoonida si loo daboolo baahiyaha saldhigga macaamiisha sii kordhaya.

2023 - 2026 Mashaariicda Dhismaha

Mashaariicda substation

PUD waxay leedahay in ka badan 100 saldhigyo iyo saldhigyo beddela dhammaan aagga adeeggayaga. Saldhigyadan hoose ayaa muhiim u ah gaarsiinta tamarta macaamiisheena. Sida saldhiga macaamiisheena u korayo, waa in aan cusboonaysiinnaa oo aan cusboonaysiinnaa saldhigyadan si aan u sii wadno bixinta adeeg la isku halayn karo. Halkan fiiri mashaariicda hoose ee hadda jira:

  • Si loo kordhiyo kalsoonida Jasiiradda Camano, PUD waxay qorsheyneysaa inay dib u dhisto Waqooyiga Camano Substation (qiyaastii la dhammaystiray 2025).
  • Si loo kordhiyo kalsoonida loona taageero rakibaadda nidaamka kaydinta tamarta batteriga mustaqbalka, PUD waxay dhisaysaa mid cusub Substation-dabaysha Xarunteeda Degmada Waqooyi ee ku taal Barta Smokey.
  • Si si wanaagsan loogu adeego baahida koronto ee waqooyiga Snohomish County, PUD ayaa horumarinaysa Saldhigga Lake Goodwin (dhamaystiran 2025) iyo iyada Saldhig Isgoysyada Stimson (dhamaystiran 2026).
  • Si loo kordhiyo awoodda Marysville, PUD waxay hadda dhisaysaa mid cusub Jennings Park Substation (dhammaystirka 2024) taas oo beddeli doonta Saldhigga dhexe ee Marysville, kaas oo la dumin doono 2025.
  • Si loo bixiyo awoodda kaydka haddii ay dhacdo in beddelka BPA uu xumaado oo lagu daro awoodda beddelka, PUD waxay dhisaysaa mid cusub Saldhigga beddelka ee Getchell (dhamaystiran 2026) ee bariga Marysville ee u dhaw Highway 9. PUD waxa ay nakhshadaynaysaa saldhigan si ay ugu ogolaato qol ilaa laba dhibcood oo BPA ah oo keenista koritaanka mustaqbalka ee degaanka woqooyiga.
  • Si ay si wanaagsan ugu adeegto qaybta bari ee aagga adeeggeeda, PUD waxay qorshaynaysaa inay cusboonaysiiso Clearview Substation (dhamaystiran 2024) iyo iyada Thrashers Corner Substation (dhamaystiran 2027).
  • Si ay si wanaagsan ugu adeegto qaybta koonfureed ee aagga adeeggeeda, PUD waxay qorshaynaysaa inay cusboonaysiiso Substation Brier (dhamaystiran 2025), iyo Substation Point Pinic (dhamaystiran 2026).

Saldhigga Eagle Creek East Arlington

Mashaariicda khadka

  • Si loo siiyo awoodda dib u celinta Jasiiradda Camano, PUD waxay dhistay mid cusub Stanwood-ilaa-Camano 115-kV (dhamaystiray 2023). Dib-u-dhiska khadka hadda jira ee 115-kV ilaa Jasiiradda Camano waxay bilaaban doontaa xagaaga 2024.
  • Si ay si wanagsan ugu adeegto baahida koronto ee qaybta waqooyi ee adeegeeda, PUD ayaa dib u dhiseysa Stimson-ilaa-Stanwood 115-kV (dhammaystirka 2025) iyo naqshadaynta iyo dhisida mid cusub Stimson-to-Sills Corner 115-kV (dhamaystiran 2026).
  • PUD waxay dhisi doontaa qayb ka mid ah kuwa cusub 115-kV xariiq si loo quudiyo saldhigga cusub ee Jennings Park gudaha Marysville (dhamaystiran 2024). Intaa waxaa dheer, PUD waxay dib u hagajin doontaa ilaa 0.75 mayl oo 115-kV ah oo u dhow saldhigga Jennings Park.
  • PUD waxay ka shaqaynaysaa fududaynta iyo dhamaystirka naqshadaynta Wajiga labaad ee xariiqda 115-kV si ay u Substation Sky Valley (dhamaystiran 2025).
  • PUD waxay qorsheyneysaa inay dhisto a laba wareeg ah 115-kV line ilaa xarunta cusub ee Crosswind ee ku taal Arlington. Mashruucani waa in lagu taageero mashruuca nidaamka kaydinta tamarta batteriga cusub (dhammaystirka 2025).
  • Si loo hagaajiyo isku halaynta, PUD waxay dib u dhisi doontaa 115-kV xariiq isku xirka Perrinville iyo Maplewood substations (dhamaystiran 2026).
  • Si loo taageero kobaca rarka iyo hagaajinta isku halaynta gudaha Everett, Marysville iyo waqooyiga Snohomish County, PUD waxay ku jirtaa marxaladaha qorsheynta ee dhismaha a cusub 115-kV xariiq ilaa saldhiga cusub ee Getchell (dhamaystiran 2027) iyo a khad cusub oo 115-kV ah laga bilaabo Everett ilaa saldhigyada Delta (dhamaystiran 2027).
  • PUD ayaa dhisi doonta 115-kV khadadka ku cusub maltby iyo saldhigyada Jannada (dhamaystiran 2028).
  • Si loo ilaaliyo adeega la isku halayn karo ee Jasiirada Hat, PUD waxa ay qorshaynaysaa in ay badasho Xadhkaha badda hoostiisa ee Hat Island (dhamaystiran 2024).

Tiirka iyo dayactirka qaybinta

Sannad kasta, PUD:

  • Sannad kasta waxa uu beddelaa ilaa 500 tiir oo gabowga ah
  • Waxay qiimeeyaan oo ay daaweeyaan in ka badan 25,000 tiir
  • Beddelayaa 20 ilaa 30 mayl ee fiilooyinka dhulka hoostiisa ee gabowga inta lagu jiro goobta adeega tamarta