Process Plan and Schedule

 

Process Plan and Schedule

      
  

Responsible Entity

  
  

Pre-Filing Milestone

  
  

Date

  
  

FERC Regulation

  

District

Issue   Public Notice for NOI/PAD

3/21/2013

5.3(d)(2)

District

File   NOI/PAD with FERC

3/21/2013

5.5,   5.6

FERC

Tribal   Meetings

4/20/2013

5.7

FERC

Issue   Notice of Commencement of Proceeding; Issue Scoping Document 1 (SD1)

5/20/2013

5.8

FERC

Site   Visit and Scoping Meetings

Site   visit – 6/12/2013; Scoping meetings – 6/12/2013 and 6/13/2013

5.8(b)(viii)

All   stakeholders

PAD/SD1   Comments and Study Requests Due

07/19/2013

5.9

FERC

Issue   Scoping Document 2

09/02/2013

5.1

District

File   Proposed Study Plan (PSP)

09/02/2013

5.11(a)

All   stakeholders

Proposed   Study Plan Meeting

10/02/2013

5.11(e)

All   stakeholders

Proposed   Study Plan Comments Due

12/01/2013

5.12

District

File   Revised Study Plan

12/31/2013

5.13(a)

All   stakeholders

Revised   Study Plan Comments Due

1/15/2014

5.13(b)

FERC

Director's   Study Plan Determination

1/30/2014

5.13(c)

USFS,   USFWS, Ecology

Any   Study Disputes Due

2/19/2014

5.14(a)

Dispute   Panel

Third   Panel Member Selected

3/6/2014

5.14(d)(3)

Dispute   Panel

Dispute   Resolution Panel Convenes

3/11/2014

5.14(d)

District

Applicant   Comments on Study Disputes Due

3/16/2014

5.14(j)

Dispute   Panel

Dispute   Resolution Panel Technical Conference

3/21/2014

5.14(j)

Dispute   Panel

Dispute   Resolution Panel Findings Issued

4/10/2014

5.14(k)

FERC

Director's   Study Dispute Determination

4/30/2014

5.14(l)

District

First   Study Season

04/14   through 10/14

5.15(a)

UDPATED SECTION, 1/30/2015

District

Initial Study   Report (ISR)

1/30/2015

5.15(c)(1)

All   stakeholders

ISR Meeting

2/11/2015 and   2/12/2015

5.15(c)(2)

District

ISR Meeting   Summary

3/1/2015

5.15(c)(3)

All   stakeholders

Any   Disputes/Requests to Amend Study Plan Due

3/31/2015

5.15(c)(4)

All stakeholders

Responses to   Disputes/Amendment Requests Due

4/30/2015

5.15(c)(5)

FERC

Director's   Determination on Disputes/Amendments

5/30/2015

5.15(c)(6)

Updated Section, 11/10/15

District

File Draft   License Application (DLA)

1/28/2016

5.16

All   stakeholders

DLA Comments   Due

4/27/2016

5.16(e)

District

File Final   License Application

Anticipated

4Q2016

 

 Updated Per FERC, 3/22/2016 Letter

 All stakeholders

 Updated Study Report Meeting

 4/21/2016

 5.15(f)

 District

 Updated Study Report Meeting Summary

 5/6/2016

 5.15(f)

 All stakeholders

 Any disputes/requests to amend study plan due

 6/5/2016

 5.15(f)

 All stakeholders

 Responses to disputes/amendment requests due

 7/5/2016

 5.15(f)

 FERC

 Director's determination on disputes/amendments

 8/4/2016

 5.15(f)
       

 

 