JHP Relicensing: Timeline

FERC Flowchart for ILP


Process Plan and Schedule, 1/24/2006

The license for the Project was issued by FERC on September 2, 2011.

Henry M. Jackson Plan and Schedule
(updated 10/15/09 FERC Order)

Responsible Party Pre-Filing Milestone Date1 FERC Regulation
PUD & City Issue Public Notice for NOI/PAD 12/1/05 5.3(d)(2)
PUD & City File NOI/PAD with FERC 12/1/05 5.5, 5.6
FERC Tribal Meetings 12/31/05 5.7
FERC Issue Notice of Commencement of Proceeding; Issue Scoping Document 11/30/06 5.8
FERC Jackson Project Site Visit and Scoping Meetings 10/17/05 (Site Visit); 2/27/06 & 2/28/06 (Scoping Meetings) 5.8(b)(viii)
All stakeholders PAD/SD1 Comments and Study Requests Due 3/31/06 5.9
FERC Issue Scoping Document 2 5/15/06 5.1
PUD & City File Proposed Study Plan (PSP) 5/15/06 5.11(a)
All stakeholders Proposed Study Plan Meeting 6/8/06 5.11(e)
All stakeholders Proposed Study Plan Comments Due 8/13/06 5.12
PUD & City File Revised Study Plan 9/12/06 5.13(a)
All stakeholders Revised Study Plan Comments Due 9/27/06 5.13(b)
FERC Director's Study Plan Determination 10/12/06 5.13(c)
USFS, USFWS, Ecology Any Study Disputes Due2 11/1/06 5.14(a)
Dispute Panel Third Panel Member Selected 11/16/06 5.14(d)(3)
Dispute Panel Dispute Resolution Panel Convenes 11/21/06 5.14(d)
PUD & City Applicant Comments on Study Disputes Due 11/26/06 5.14(j)
Dispute Panel Dispute Resolution Panel Technical Conference 12/1/06 5.14(j)
Dispute Panel Dispute Resolution Panel Findings Issued 12/21/06 5.14(k)
FERC Director's Study Dispute Determination 1/10/07 5.14(l)
PUD & City First Study Season 4/07 through 10/07 5.15(a)
PUD & City Initial Study Report 10/12/07 5.15(c)(1)
All stakeholders Initial Study Report Meeting 10/27/07 5.15(c)(2)
PUD & City Initial Study Report Meeting Summary 11/11/07 5.15(c)(3)
All stakeholders Any Disputes/Requests to Amend Study Plan Due 12/11/07 5.15(c)(4)
All stakeholders Responses to Disputes/Amendment Requests Due 1/10/08 5.15(c)(5)
FERC Director's Determination on Disputes/Amendments 2/9/08 5.15(c)(6)
All stakeholders Interim Comment Period - File any requests to amend study plan with FERC Due 3/14/08 2/5/08 FERC Determination
PUD & City Interim Comment Period - File response to requests with FERC 4/14/08 2/5/08 FERC Determination
FERC Interim Comment Period - Issue Director’s Determination on Amendment requests 5/14/08 2/5/08 FERC Determination
PUD & City Second Study Season 4/08 through 10/08 5.15(a)
PUD & City Updated Study Report due 10/11/08 5.15(f)
All stakeholders Updated Study Report Meeting 10/26/08 5.15(f)
PUD & City Updated Study Report Meeting Summary 11/10/08 5.15(f)
All stakeholders Any Disputes/Requests to Amend Study Plan Due 12/10/08 5.15(f)
All stakeholders Responses to Disputes/Amendment Requests Due 1/9/09 5.15(f)
FERC Director's Determination on Disputes/Amendments 2/08/09 5.15(f)
PUD & City File Preliminary Licensing Proposal 12/31/08 5.16(a)
All stakeholders Preliminary Licensing Proposal Comments Due 3/31/09 5.16(e)
PUD & City File Final License Application 5/30/09 5.17
PUD & City Issue Public Notice of License Application Filing 6/13/09 5.17(d)(2)
Responsible Party Post-Filing Milestone Date1 FERC Regulation
FERC Issue Public Notice of License Application Filing (Tendering Notice) 6/13/09 5.19
FERC Director's Determination on Any Additional Study Requests and Notification of Any Deficiencies 6/29/09 5.19(e); 5.20(a)(2)
FERC Issue Public Notice Accepting Application and Ready for Environmental Analysis (REA) 7/29/09 5.22
All stakeholders Comments, Interventions, 10(a) Recommendations Due 11/6/09 5.23(a)
Agencies 10(j) Recommendations; 4(e) Terms and Conditions; Fishway Prescriptions Due 11/6/09 5.23(a)
PUD & City Request 401 Water Quality Certification from Ecology 9/27/09 5.23(b)
PUD & City Reply Comments Due 12/21/09 5.23(a)
FERC Issue Single Environmental Assessment (EA)3 5/5/10 5.24
All stakeholders Single EA Comments Due 6/4/10 5.24(c)
Agencies USFS Modified 4(e) Terms and Conditions Due;
USFWS Modified Fishway Prescriptions Due
8/3/10 5.24(d)
FWS/NMFS ESA Biological Opinion As Needed 7/24/10 ESA
FERC Issue Final EA 11/1/10 FPA

1       If the due date falls on a weekend or holiday, the due date is the following business day.
2       Shaded milestones are unnecessary if there are no study disputes.
3       This schedule assumes FERC will issue a “single” EA (without a draft EA).  If FERC determines that a draft EA is needed, the post-filing timeframes will be modified accordingly.
* Updated to include Interim Comment Period dates.